  1. We will address the previous challenges and resolve the current bugs in the existing codebase.

  2. The WordPress site will be removed from the server and maintained by a different team.

  3. The develop and production servers will be scaled up and moved to Azure and we will incur the charges.

    1. We will give MCCC the SSH keys and/or access to the resource group in Azure so that you can have control of the data and server if needed.

    2. The original servers can remain up and running or saved as images in Digital Ocean.

  4. We will setup version control using the current GitHub repository and ensure that the code in the repo and on the servers stay in sync.

  5. We will create a pipeline for handling releases from develop to production servers. → ideally triggerable by MCCC.

Fixing the issues identified in the GitHub repo

...

  1. Priority 1 - Emergency

  2. Priority 2 - Fix Soon

  3. Priority 3 Active Mainenance

Will get together with Anna and Juliet to prioritize issues before starting.

Timeline

  1. Setting up the new servers and pipelines → 2-3 weeks.

  2. Fixing the issues listed in GitHub → 3-4 weeks.

  3. Switch DNS to new server → 10 minutes.