Introduction
This document will go over the timeline and scope of Western Species Selector tool completion and testing.
User testing timeline proposal
Meeting to kick off scope and plan for user testing the week February 3rd (to be scheduled)
The tool will have all western data for all councils imported by February 28th
Starting March 1st we will have a small internal review from members of the WCCC to make sure things are working as expected and resolve any issues
User testing materials will start being created in early March and be completed by March 15th
Final materials will be delivered to facilitators on March 22nd
User testing will begin the week of March 24th and complete April 11th
Results will be summarized on May 2nd
Any updates needed from user testing will be implemented in May and June
Helpful documents
These documents are from previous rounds of user testing, so there may be some updates for WCCC testing.