Next Steps for User Testing

Week of May 20th

GameTheory send outs goals document and survey to collect feedback on the goals from individuals fulfilling the key project roles
Team confirms if GameTheory will provide Testing Materials

Week of May 27th - June 7th

DUE MONDAY MORNING: All Testing Goals survey’s submitted.
GameTheory edits Goals & Approach based on survey responses
GameTheory creates final Goals & Approach document for approval

Week of June 10th

Testing Materials are drafted
GameTheory meets to review testing materials and support production
GameTheory prepares Testing Management structure to support Async and 1-on-1 User Testing.

Week of June 17th

Testing Materials are finalized.
GameTheory supports on reviewing Testing Materials for finalization.
GameTheory prepares Testing Management structure to support Testing Approach

Week of June 24th

GameTheory ensures AB or ABC testing materials are ready for testing.
Testing materials distributed

July

Testing begins! Testing deadline August 15.
GameTheory supports testing in the Testing Manager role

Future Weeks (June - July)

  • GameTheory provides ongoing support as Testing Managers

  • GameTheory collects and correlates feedback as it is received